The factors for planning a successful EHR implementation are below including each activity's duration and predecessor(s): Draw the PERT or GANTT chart for this implementation Indicate the critical path on the PERT or GANTT chart
Activity
Duration (days)
Predicessor
A
Create the EHR vision
5
-
B
Identify the planning horizon
10
A
C
Obtain buy-in from affected parties
30
B
D
Develop a financing and acqusition strategy
10
C
E
Develop functional, datda, and technical strategies
45
C
F
Conduct vendor selection
45
D,E
G
Plan the EHR implementation
15
C,E, F
H
Conduct benefits realization study
10
A- H