question archive Madrid FC own land in the metropolitan area of Madrid
Subject:ManagementPrice: Bought3
Madrid FC own land in the metropolitan area of Madrid. They would like to build a sports complex which would include state-of the art training facilities for elite athletes. Your consultancy office with the help of architects and sports consultant have drawn up three different projects) (i) 10 hectare site with small capacity for athletes (ii) 20 Ha site and moderate level of capacity; (iii) a high-level complex at 30 Ha.
The success of the project depends upon several factors. Madrid FC want to build make the largest profit. There is uncertainty concerning the demand for the three projects. The decision is to select the optimum project depends on following three decision alternatives:
Decision 1: a small sports complex at 10 Ha Decision 2: a medium complex at 20 Ha Decision 3: a large complex at 30 Ha
Some other information investigated:
Decision 1 would be in the centre of town where property and land are expensive but would have some kudos as it is close to the football ground.
Decision 2 is close to the centre but transport would be needed to get to it. Decision 3 is out of town with lots of opportunity for expansion.
A study was conducted to get some prior knowledge for the probability of each alternative occurring at 2 different demand level. The two directions investigated were high demand and low demand and based on various financial metrics and a probability assigned to these variables (see table 1 below).
Thus, management must first select a decision alternative (complex size), then other states of nature will be investigated e.g. (demand for the sports facility). Given the three decision alternatives and the two states of nature, which sports complex should Madrid FC advance?
To answer this question, Madrid FC will need to know the consequence associated with each decision alternative and each state of nature.
Table 1: Payoff for Madrid FC Sports Complex (payoff in Euros million)
Low Demand
High Demand
Size
Decision
S1 (p=0.4)
S2 (p=0.6)
Small
D1
3000
3200
Medium
D2
2500
2800
Large
D3
2000
2100
Table 2: A survey was completed with 100 people that showed strong interest in signing up to train at the complex. A contingency table of the data is shown below
Trains more than 3 times a week
Trains less than 3 times a month
TOTAL
Football fan
20
40
60
Non-football fan
20
20
40
TOTAL
40
60
100
Questions: