question archive Amman The following are machine hours and the maintenance and repair costs of Corporation: Machine hours maintenance and repair costs January 1500 hours $ 9700 February 1200 9600 March 2000 10000 Using the high-low method, the variable cost per machine hour is: O A

Amman The following are machine hours and the maintenance and repair costs of Corporation: Machine hours maintenance and repair costs January 1500 hours $ 9700 February 1200 9600 March 2000 10000 Using the high-low method, the variable cost per machine hour is: O A

Subject:AccountingPrice:2.84 Bought6

Amman The following are machine hours and the maintenance and repair costs of Corporation: Machine hours maintenance and repair costs January 1500 hours $ 9700 February 1200 9600 March 2000 10000 Using the high-low method, the variable cost per machine hour is: O A. $0.40 O B. $0.24 O C. $0.50 D. None of the above

pur-new-sol

Purchase A New Answer

Custom new solution created by our subject matter experts

GET A QUOTE

Answer Preview

         
  Under High low method,Consider the Highest and Lowest activity and then apply the following equation
  Variable cost per machine hour=Change in maintance and repair costs/Change in machine hours
  Highest activity is in March-2000 machine hours
  Lowest activity is in Feb-1200 machine hours
  Variable cost per machine hour=(10000-9600)/(2000-1200)=$ 0.50
           
  Answer is      
  c. $0.50