question archive Shown below data about four quarters of 2020 budget for X Company: Third quarter Fourth quarter cost of material 40000 50000 -70% of quarter's purchases is paid for in the quarter of purchases and the remaining 30% is paid for in the following quarter
Subject:AccountingPrice:2.84 Bought3
Shown below data about four quarters of 2020 budget for X Company: Third quarter Fourth quarter cost of material 40000 50000 -70% of quarter's purchases is paid for in the quarter of purchases and the remaining 30% is paid for in the following quarter. Cash disbursement schedule for fourth quarter would be: O A. $24900 B. $47000 O C. $35600 D. none of the above
Cash disbursement schedule for fourth quarter would be :- (B) $47,000.
3rd Quarter | 4th Quarter | |
Cost of Material | 40,000 | 50,000 |
Cash Disbursement | 47,000 |
($50,000*70%)+($40,000*30%) = $47,000.