question archive The following text applies to the questions at positions 33, 34, 35, 36, 37, 38, 39, 40, 41 Instructions: Please read and answer the attached questions Earned Value Management (EVM3)   You are working on a project that is scheduled to be completed in 10 months

The following text applies to the questions at positions 33, 34, 35, 36, 37, 38, 39, 40, 41 Instructions: Please read and answer the attached questions Earned Value Management (EVM3)   You are working on a project that is scheduled to be completed in 10 months

Subject:Project ManagementPrice: Bought3

The following text applies to the questions at positions 33, 34, 35, 36, 37, 38, 39, 40, 41

Instructions: Please read and answer the attached questions

Earned Value Management (EVM3)

 

You are working on a project that is scheduled to be completed in 10 months. The total budget for the project is $10,000Six months have passed and the schedule indicates that 60% of the work should be completed by now. But your team has only completed 50% of the project and spent $8,000.  

 

Question at position 33 

What is the Planned Value (PV) for this project at this point in time?

What is the Planned Value (PV) for this project at this point in time?

$10,000 * 60% = $6,000

 

$10,000 * 50% = $5,000

 

$8,000 * 60% = $4,800

 

$8,000 * 50% = $4,000

 

Question at position 34 

What is the Earned Value (EV) for this project at this point in time?

What is the Earned Value (EV) for this project at this point in time?

$10,000 * 50% = $5,000

 

$8,000 * 60% = $4,800

 

$10,000 * 60% = $6,000

 

$8,000 * 50% = $4,000

 

Question at position 35 

What is the Cost Performance Index (CPI) for this project?

What is the Cost Performance Index (CPI) for this project?

CPI = .625

 

CPI = .833

 

CPI = 1.6

 

CPI =1.2

pur-new-sol

Purchase A New Answer

Custom new solution created by our subject matter experts

GET A QUOTE