question archive A rush order was accepted by Ty-Nee Trailer Company for five trailers
Subject:AccountingPrice:3.87 Bought7
A rush order was accepted by Ty-Nee Trailer Company for five trailers. The time tickets and clock cards for the 2-week period ended March 30 show the following:
Time TIckets Hour Distribution
Previous Trailer Trailer Trailer Trailer Trailer
Employees Hrs Earnings #1 #2 #3 #4 #5
Castro 80 P16,800 all time spent supervising
Ardina 85 15,500 20 20 15 15 15
Briones 88 15,000 24 24 23 10 6
David 88 13,500 18 16 20 20 12
Fajardo 85 12,800 10 15 18 25 17
All workers are paid P150/hr, except Ardina, who receives P160/hr. All overtime premium pay except Ardina's is chargeable to the job and all workers, including Ardina, received TIME and a HALF for overtime pay. Hours not worked on trailers are charged to factory overhead.