question archive A software company launches software for an organization which produces 1000 lines of code with the labor rate of $30000 per persons-month use the function decomposition technique to estimates its efforts and what is the required cost to create the software using estimation technique?
Subject:Computer SciencePrice:2.89 Bought3
A software company launches software for an organization which produces 1000 lines of code with the labor rate of $30000 per persons-month use the function decomposition technique to estimates its efforts and what is the required cost to create the software using estimation technique?
Given,
Lines of code= 1000
Labor rate = $30000
Efforts= 1.4L0.93 = 1.4 (1000)0.93 = 863.23 person per month where a= 1.4, b= 0.93 are constant
Efforts = 863.23 person-months
Costs =labor rate/ lines of code = 30000/1000 = $30 cost per line of code
Costs to create the software using ET = $30* 863.23 = $25,869.6