question archive Management wants to design an assembly line that will turn out 800 videotapes per day
Subject:Operations ManagementPrice:2.87 Bought7
Management wants to design an assembly line that will turn out 800 videotapes per day. There will be eight working hours in each day. The industrial engineering staff has assembled the information below:
(A) Determine the maximum and minimum cycle times.
(B) Determine the optimum cycle time.
(C) What is the minimum number of stations needed?
(D) Draw the precedence diagram.
(E) Assign tasks to stations in order of most following tasks first.
task |
time(min) |
immediate predecessor |
a | 2 | none |
b | 2 | a |
c | 4 | none |
d | 1 | none |
e | 3 | c, d |
f | 2 | b, e |
g | 1 | none |
h | 2 | f, g |
i | 6 | h |
please use this google drive link to download the answer file.
https://drive.google.com/file/d/1XMsEB-l9dxFowX20afIeyCF7kQLX5k4C/view?usp=sharing
note: if you have any trouble in viewing/downloading the answer from the given link, please use this below guide to understand the whole process.
https://helpinhomework.org/blog/how-to-obtain-answer-through-google-drive-link