question archive During the construction of a recent office building, your company’s framing crew installed 515 lineal feet of 8-foot-high, metal-stud wall in two days
Subject:Civil EngineeringPrice:2.87 Bought7
During the construction of a recent office building, your company’s framing crew installed 515 lineal feet of 8-foot-high, metal-stud wall in two days. The crew consisted of two carpenters and one helper and worked eight hours per day. Determine productivity rate in labor hours per foot of wall for installing metal-stud walls on this project.
Answer:
total labours are (2+1)= 3
total working in hour = 2 * 8=16 hour
total lineal installed is 515 *8=4120 feet productivity in labour hrs per foot is
3*16/4120 labour hrs per foot