question archive During the construction of a recent office building, your company’s framing crew installed 515 lineal feet of 8-foot-high, metal-stud wall in two days

During the construction of a recent office building, your company’s framing crew installed 515 lineal feet of 8-foot-high, metal-stud wall in two days

Subject:Civil EngineeringPrice:2.87 Bought7

During the construction of a recent office building, your company’s framing crew installed 515 lineal feet of 8-foot-high, metal-stud wall in two days. The crew consisted of two carpenters and one helper and worked eight hours per day. Determine productivity rate in labor hours per foot of wall for installing metal-stud walls on this project.

pur-new-sol

Purchase A New Answer

Custom new solution created by our subject matter experts

GET A QUOTE

Answer Preview

Answer:

total labours are (2+1)= 3

total working in hour = 2 * 8=16 hour

total lineal installed is 515 *8=4120 feet productivity in labour hrs per foot is

3*16/4120  labour hrs per foot