question archive A labor crew for placing concrete consists of one labor foreman at $26

A labor crew for placing concrete consists of one labor foreman at $26

Subject:EconomicsPrice:2.84 Bought7

A labor crew for placing concrete consists of one labor foreman at $26.09 per hour, one cement finisher at $29.30 per hour, 4 laborers at $24.45 per hour each, and one equipment operator at $34.9 per hour. Such a crew, called a C20 crew, can place 160 cubic yards of concrete per 8-hour day.

Determine the cost per day of labor for the C20 crew.

The cost per day is determined to be $  .

pur-new-sol

Purchase A New Answer

Custom new solution created by our subject matter experts

GET A QUOTE

Answer Preview

$1504.72

Step-by-step explanation

Cost per day of labor for the crew=cost per hour of labor for the crew*hours worked per day

 

Cost per hour of labor for the crew =26.09+29.30+(4*24.45)+34.9=$188.09

 

Cost per day of labor for the crew=188.09*8=$1504.72

 

Cost per day is determined to be $1504.72