A labor crew for placing concrete consists of one labor foreman at $26.09 per hour, one cement finisher at $29.30 per hour, 4 laborers at $24.45 per hour each, and one equipment operator at $34.9 per hour. Such a crew, called a C20 crew, can place 160 cubic yards of concrete per 8-hour day.
Determine the cost per day of labor for the C20 crew.
The cost per day is determined to be $ .
$1504.72
Step-by-step explanation
Cost per day of labor for the crew=cost per hour of labor for the crew*hours worked per day
Cost per hour of labor for the crew =26.09+29.30+(4*24.45)+34.9=$188.09
Cost per day of labor for the crew=188.09*8=$1504.72
Cost per day is determined to be $1504.72