question archive Question 37                 Project A has NPV of $1,200, IRR 14

Question 37                 Project A has NPV of $1,200, IRR 14

Subject:FinancePrice:2.88 Bought30

Question 37                
Project A has NPV of $1,200, IRR 14.50 and costs $200,000. Project B has NPV of $1,000, IRR of 22% and
costs $100,000. Project C has NPV of $1500, IRR of 17.25% and costs of $175,000. Project D has NPV of
$1000, IRR of 8.90% and costs of $200,000. If the firm has a capital budget of $375,000 which projects
should it take by NPV criteria:   NPV IRR Costs      
A. A and B   A 1200 14.5 200000      
B. A and C   B 1000 22 100000      
C. B and D   C 1500 17.25 175000      
D. C and D   D 1000 8.9 200000

Option 1

Low Cost Option
Download this past answer in few clicks

2.88 USD

PURCHASE SOLUTION

Option 2

Custom new solution created by our subject matter experts

GET A QUOTE

rated 5 stars

Purchased 30 times

Completion Status 100%