question archive Continued from previous question
Subject:FinancePrice: Bought3
Continued from previous question. If the company's cost of capital is 5% and the decision is made by choosing the project with the higher IRR, how much value will be forgone? (Hint: Complete the NPV profile)
Select one:
a. $12.45
b. $20.80
c. $ 4.01
d. $29.89
e. $ 1.79
Continued from previous question. Which of the following statements is correct?
Select one:
a. The crossover rate should be between 15% and 20%.
b. The crossover rate should be between 10% and 15%.
c. If the WACC is smaller than the crossover rate, you will choose project S using the NPV method.
d. If the WACC is larger than the crossover rate, a conflict arises between the NPV and the IRR methods.
e. The crossover rate should be smaller than 10%.