question archive ABC Company Extreme Lawn Mower The project charter is a document issued by the project initiator or sponsor that formally authorized the existence of a project, and provides the project manager with the authority to apply organizational resources to project activities
Subject:ManagementPrice: Bought3
ABC Company Extreme Lawn Mower
The project charter is a document issued by the project initiator or sponsor that formally authorized the existence of a project, and provides the project manager with the authority to apply organizational resources to project activities.
Project Sponsor: Your Professor
Project Manager: You
Project Customer: All ABC Company Customers
Date Prepared: Today’s date
Project Purpose and Justification: There has been a number of customers in our market space that are seeking a high-end riding lawn mower. This is a niche market of 10% of the total lawn mower market. The Return On Investment (ROI) has showed conclusively a positive return over the first eight years of the product life cycle. This new product introduction is aligned with ABC company’s long-term strategic plan. |
High-Level Project and Product Requirements: Reliable, high efficiency, 35 horsepower engine Luxurious cab Dash with complete set of gauges High performance engine High performance cutting system |
Summary Budget: The budget is not to exceed 1 million dollars. This is considered a hard constrain. The project is not to exceed one year in length. This is considered a hard constrain. |
Initial Risks:
|
Summary Milestones | Due Date |
Exploration | TBD |
Design | TBD |
Go-no-go | TBD |
Prototype Development | TBD |
Go-no-go | TBD |
Development | TBD |
End user testing | TBD |
Launch | TBD |
Marketing | TBD |
Project Objective | Success Criteria | Person Approving |
Scope | New Product development and introduction | |
Time | Less than 1 year | |
Cost | Less than 1 million dollars | |
Quality | Must meet all internal quality standards (this is to be documented in the WBS) | |
Other | ||
Acceptance Criteria: There are to be a number of Go-No-Go milestones within the project WBS (after each major phase) Must meet all CAA reguirments |
Project Manager Authority Level
Staffing decisions Budging management Schedule management Change control process owner Project communications |
Technical Decisions: TBD |
Conflict Resolution: TBD |
Escalation Process: To be created formally and listed in the WBS (this is a new process for ABC Company) |
Authority Limitations: Project Manager to report and gain approval for any increase or decrease in project budget of 10K or a schedule change of + or - 15 days |
Approvals:
________________________________________ ________________________________________
Project Manager Signature Sponsor Signature
________________________________________ ________________________________________
Project Manager Name Sponsor Name
________________________________________ ________________________________________
Date Date
Prepared by: Tel. No: Email ID: |