question archive During year 1, XYZ Construction Company started work on a $3 million construction contract that was completed in Year 2

During year 1, XYZ Construction Company started work on a $3 million construction contract that was completed in Year 2

Subject:AccountingPrice:6.89 Bought3

  1. During year 1, XYZ Construction Company started work on a $3 million construction contract that was completed in Year 2. The accounting records include the following information:

..................................................................................................................Year 1..........................................Year 2

Costs incurred to date...............................................................900,000..................................2,720,000

Estimated cost to complete contract.................................1,800,000................................. -

 

A. How much percent of the work is completed during year 2?

B How much contract revenue should XYZ construction company have recognized in year 1 if the method was percentage of completion method?

C. How much growth profit should have recognized in year 1 if the method was percentage of completion method?

D. How much growth profit should have recognized in year 1 if the method was completed contract?

E. How much growth profit is recognized in year 2 if the method was completed contract?

F. How much is the construction - in - progress account under percentage of completion method at the end of year 1?

pur-new-sol

Purchase A New Answer

Custom new solution created by our subject matter experts

GET A QUOTE

Answer Preview

A. How much percent of the work is completed during year 2?

 

= 100% - 33.33%

= 66.67%

 

B How much contract revenue should XYZ construction company have recognized in year 1 if the method was percentage of completion method?

 

= 1,000,000 

 

C. How much growth profit should have recognized in year 1 if the method was percentage of completion method?

 

=100,000

 

D. How much growth profit should have recognized in year 1 if the method was completed contract?

 

= Nil (Since contract is not complete at end of year 1)

 

E. How much growth profit is recognized in year 2 if the method was completed contract?

 

= 280,000

 

F. How much is the construction - in - progress account under percentage of completion method at the end of year 1?

 

= 900,000