During the construction of a recent office building, your company’s framing crew installed 515 lineal feet of 8-foot-high, metal-stud wall in two days

Subject:Civil EngineeringPrice:2.87 Bought7

During the construction of a recent office building, your company’s framing crew installed 515 lineal feet of 8-foot-high, metal-stud wall in two days. The crew consisted of two carpenters and one helper and worked eight hours per day. Determine productivity rate in labor hours per foot of wall for installing metal-stud walls on this project.

Select one:

a. 0.093 lhr/lft

b. 0.084 lhr/lft

c. 0.102 lhr/lft

d. None of the above