Problem Assignment (Project Scheduling)
#1) (6 points)
Following information is available about a project.
Activity |
Activity Time (weeks) |
Immediate Predecessor(s) |
A |
4 |
- |
B |
4 |
- |
C |
5 |
- |
D |
4 |
- |
E |
6 |
A |
F |
2 |
B,C,D |
G |
4 |
E.F |
H |
6 |
F |
I |
1 |
G,H |
Compute slack for noncritical activities for the project and enter them in the table below.
NOTE: Some rows in table below may be blank.
Activity |
Slack |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
#2) (6 points) Activity durations (in weeks) for a project are given below:
|
|
|
|
|
|
|
Activity |
Precedence |
Optimistic time |
Most likely time |
Pessimistic time |
Expected time |
Variance |
A |
- |
6 |
7 |
14 |
8.00 |
1.78 |
B |
- |
8 |
10 |
12 |
10.00 |
0.44 |
C |
- |
2 |
3 |
4 |
3.00 |
0.11 |
D |
A |
6 |
7 |
8 |
7.00 |
0.11 |
E |
B, C |
5 |
5.5 |
9 |
6.00 |
0.44 |
F |
B, C |
5 |
7 |
9 |
7.00 |
0.44 |
G |
D, E |
4 |
6 |
8 |
6.00 |
0.44 |
H |
F |
2.5 |
3 |
3.5 |
3.00 |
0.03 |
What is the probability that the project will finish 1 week early? Perform the necessary calculations and complete entries in the table below.
NOTE: Some rows in table below may be blank.
Path |
Probability finishing the project 1 week early |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Joint probability of completing the project 1 week early = _________
#3) (6 points)
Project description: You are hired by the SCM Faculty Coordinator to move old offices of four SCM faculty/staff from the 3rd floor (Hyland Hall) to new offices on the 4th floor (Hyland Hall).
Office |
Estimated number of boxes |
#1 |
10 |
#2 |
10 |
#3 |
5 |
#4 |
5 |
Tasks and estimated task times are as follows:
Packing and labeling boxes - 6 minutes per box
Loading boxes into dolly - 1 minute per box
Moving loaded dolly (1 trip) from 3rd floor to 4th floor - 20 minutes.
Unloading boxes into offices - 1 minute per box
Moving empty dolly (1 trip) from 4th floor to 3rd floor - 10 minutes
Cleaning all old offices – total of 60 minutes
Strategy
COMPLETE TABLES BELOW.
Person #1 – Work Sequence (Office #): 1, 2, 3, 4
Work package #1: Pack and label boxes in old office
Person #1 Schedule:
Office |
Work package #1 Start time |
Work package #1 Finish time |
#1 |
|
|
#2 |
|
|
#3 |
|
|
#4 |
|
|
Person #2 – Work Sequence (Office #): 1, 2, 3, 4, 5, 6
Work package #2 (in sequence): Load boxes on dolly, Move dolly to new office, Unload boxes in new office and Move dolly back to 3rd floor.
NOTE: Person #2 cannot start loading dolly until all boxes in an office is packed and labeled.
Person #2 Schedule:
Office |
Loading-Moving- Unloading Start time |
Loading-Moving-Unloading Finish time |
Dolly return to 3rd floor |
#1 |
|
|
|
#2 |
|
|
|
#3 |
|
|
|
#4 |
|
|
|
Person #1 – Work package #3: Clean all old offices at the end of the day.
Person #1 Schedule (Work package #3)
Work package #3 |
Work package #3 Start time |
Work package # Finish time |
Clean all offices |
|
|