question archive Problem Assignment (Project Scheduling) #1) (6 points) Following information is available about a project

Problem Assignment (Project Scheduling) #1) (6 points) Following information is available about a project

Subject:Project ManagementPrice:22.99 Bought15

Problem Assignment (Project Scheduling)

#1) (6 points)

Following information is available about a project.

Activity

Activity Time (weeks)

Immediate Predecessor(s)

A

4

-

B

4

-

C

5

-

D

4

-

E

6

A

F

2

B,C,D

G

4

E.F

H

6

F

I

1

G,H

 

 

 

 

 

 

 

 

 

 

 

Compute slack for noncritical activities for the project and enter them in the table below.

NOTE: Some rows in table below may be blank.

 

Activity

Slack

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

#2) (6 points) Activity durations (in weeks) for a project are given below:

 

 

 

 

 

 

 

 

 

Activity

Precedence

Optimistic

time

Most likely time

Pessimistic

time

Expected time

Variance

A

-

6

7

14

8.00

1.78

B

-

8

10

12

10.00

0.44

C

-

2

3

4

3.00

0.11

D

A

6

7

8

7.00

0.11

E

B, C

5

5.5

9

6.00

0.44

F

B, C

5

7

9

7.00

0.44

G

D, E

4

6

8

6.00

0.44

H

F

2.5

3

3.5

3.00

0.03

 

 

What is the probability that the project will finish 1 week early? Perform the necessary calculations and complete entries in the table below.

 

 

 

 

 

 

 

 

 

 

NOTE: Some rows in table below may be blank.

 

Path

Probability finishing the project 1 week early

 

 

 

 

 

 

 

 

 

 

 

 

 

 

     

Joint probability of completing the project 1 week early = _________

 

#3) (6 points)

Project description: You are hired by the SCM Faculty Coordinator to move old offices of four SCM faculty/staff from the 3rd floor (Hyland Hall) to new offices on the 4th floor (Hyland Hall).

  1. Items include books, computers, printers and other miscellaneous items. Furniture such as desks, cabinets and bookshelves are not to be moved.
  2. Unlimited boxes are available.
  3. Unpacking boxes is not part of the project.
  4. Offices on the 4th floor are move-in ready.

 

Office

Estimated number of boxes

#1

10

#2

10

#3

5

#4

5

 

Tasks and estimated task times are as follows:

Packing and labeling boxes - 6 minutes per box

Loading boxes into dolly - 1 minute per box

Moving loaded dolly (1 trip) from 3rd floor to 4th floor - 20 minutes.

Unloading boxes into offices - 1 minute per box

Moving empty dolly (1 trip) from 4th floor to 3rd floor - 10 minutes

Cleaning all old offices – total of 60 minutes

 

Strategy

  1. Hyland Hall opens at 5:30 am and closes at 5:30 pm.
  2. Work hours: Starts at 6:00 am;
  3. One dolly (capacity 10 boxes per dolly) is available.
  4. Dolly is “parked” on 3rd floor. Dolly needs to be returned to 3rd floor after all offices are handed over.
  5. Person #1 – Work package #1: Pack and label boxes in old office. Person works on one office until it is completed.
  6. Person #2 – Work package #2 (in sequence): Move boxes from old office to new office (i.e. Load boxes on dolly, Move dolly to new office and Unload boxes in new office, Move dolly back to 3rd floor). Person works on one office until it is completed. NOTE that Person #2 cannot start loading dolly until all boxes for an office is packed and labeled.
  7. Person #1 – Work package #3: Clean all old offices (at the end of the day i.e. after packing and labeling of boxes in all offices are completed).

 

COMPLETE TABLES BELOW.

 

Person #1 – Work Sequence (Office #): 1, 2, 3, 4

Work package #1: Pack and label boxes in old office

 

Person #1 Schedule:

 

Office

Work package #1 Start time

Work package #1 Finish time

#1

 

 

#2

 

 

#3

 

 

#4

 

 

 

Person #2 – Work Sequence (Office #): 1, 2, 3, 4, 5, 6

Work package #2 (in sequence): Load boxes on dolly, Move dolly to new office, Unload boxes in new office and Move dolly back to 3rd floor.

NOTE: Person #2 cannot start loading dolly until all boxes in an office is packed and labeled.

 

Person #2 Schedule:

Office

Loading-Moving- Unloading

Start time

Loading-Moving-Unloading Finish time

Dolly return to 3rd floor

#1

 

 

 

#2

 

 

 

#3

 

 

 

#4

 

 

 

 

Person #1 – Work package #3: Clean all old offices at the end of the day.

 

Person #1 Schedule (Work package #3)

 

Work package #3

Work package #3 Start time

Work package # Finish time

Clean all offices

 

 

 

 

Option 1

Low Cost Option
Download this past answer in few clicks

22.99 USD

PURCHASE SOLUTION

Option 2

Custom new solution created by our subject matter experts

GET A QUOTE

rated 5 stars

Purchased 15 times

Completion Status 100%