The production confirmation step, which begins on page 39 of the exercise, updates the order status to confirmed

Subject:BusinessPrice: Bought3

The production confirmation step, which begins on page 39 of the exercise, updates the order status to confirmed.  It also posts labour and other activity costs to the order, based on the activity time and expected costs per unit time.  In the exercise, you changed the start time to one hour earlier than scheduled, but left the completion time as indicated.  This means that the production took an hour longer than expected.  What impact did this have on the actual costs of the production order, as compared to the planned costs?  Review your screen prints from above if you need hints. 