question archive Question 4) A project has an initial outlay of $2,907

Question 4) A project has an initial outlay of $2,907

Subject:AccountingPrice:2.86 Bought11

Question 4) A project has an initial outlay of $2,907. It has a single payoff at the end of year 4 of $6,572. What is the net present value (NPV) of the project if the company's cost of capital is 14.55 percent?

Round the answer to two decimal places.

Answer:

pur-new-sol

Purchase A New Answer

Custom new solution created by our subject matter experts

GET A QUOTE

Answer Preview

The net present value (NPV) of the project = $909.96

Step-by-step explanation

Initial outlay = $2,907

NPV = Present value of cashflow - Initial outlay

Present value of cashflow = Future amount / ( 1 + r)n

r = 14.55% = 0.1455

n = 4

Future amount = $6,572

= $6,572 / ( 1 + 0.1455)4

= $6,572 / 1.14554

= $6,572 / 1.721790765

= $3,816.956237

NPV

= $3,816.956237 - $2,907

= $909.9562375

= $909.96