Which of the following statements is correct about the relationship between technical performance and Earned Value Management (EVM)?
A. Technical Performance Measurement (TPM) analysis can give early warning of issues that might impact cost and schedules performance.
B. Technical performance measures do not provide early warning of problems, whereas EVM data does
C. EVM performance data and technical performance do not deal with the same contract scope of work.
D. Technical performance should not be considered in conjunction with EVM analysis
Option A is the correct answer. I.e Technical Performance Measurement (TPM) analysis can give early warning of issues that might impact cost and schedules performance.