question archive Frandec Company manufactures, assembles, and rebuilds material handling equipment used in warehouses and distribution centers

Frandec Company manufactures, assembles, and rebuilds material handling equipment used in warehouses and distribution centers

Subject:BusinessPrice:5.87 Bought7

Frandec Company manufactures, assembles, and rebuilds material handling equipment used in warehouses and distribution centers. One product, called a Liftmaster, is assembled from four components: a frame, a motor, two supports, and a metal strap. Frandec’s production schedule calls for 4000 Liftmasters to be made next month. Frandec purchases the motors from an outside supplier, but the frames, supports, and straps may be either manufactured by the company or purchased from an outside supplier. Manufacturing and purchase costs per unit are shown.

Component Manufacturing Cost Purchase Cost
Frame $32.00 $45.00
Support $9.50 $13.00
Strap $6.50 $7.50

Three departments are involved in the production of these components. The time (in minutes per unit) required to process each component in each department and the available capacity (in hours) for the three departments are as follows:

Department
Component Cutting Milling Shaping
Frame 2.9 1.9 2.5
Support 1.2 1.5 2
Strap 0.8 1.5
Capacity (hours) 330 390 640

a. Formulate and solve a linear programming model for this make-or-buy application. How many of each component should be manufactured and how many should be purchased?

Let  
  FM = number of frames manufactured
  FP = number of frames purchased
  SM = number of supports manufactured
  SP = number of supports purchased
  TM = number of straps manufactured
  TP = number of straps purchased
Min ___________FM + ____________FP + ___________SM + ___________SP + ___________TM + ___________TP    
s.t.                          
  2.9FM     + ___________SM     + ___________TM     ___________
  ___________FM     + 1.5SM             ___________
  ___________FM     + ___________SM     + 1.5TM     ___________
  FM + ___________FP                 ___________
          SM + ___________SP         ___________
                  TM + ___________TP ___________
FM, FP, SM, SP, TM, TP ≥ 0

If required, round your answers to the nearest whole number.

  Manufacture Purchase
Frames _____?____ ____?_____
Supports _____?____ ____?_____
Straps _____?____ ____?_____

b. What is the total cost of the manufacturing and purchasing plan? When required, round your answer to the nearest dollar.

$   _______________?

c. How many hours of production time are used in each department? If required, round your answer to two decimal places.

Department Hours of production
time used
Cutting _________hours
Milling _________hours
Shaping _________hours

d. How much should Frandec be willing to pay for an additional hour of time in the shaping department? If required, round your answer to two decimal places.

$__________ because there is (slack/ surplus) of __________ hours.

e. Another manufacturer has offered to sell frames to Frandec for $39 each. Could Frandec improve its position by pursuing this opportunity?

(Yes/ No)

Why or why not? If required, round your answers to the nearest cent.

Option 1

Low Cost Option
Download this past answer in few clicks

5.87 USD

PURCHASE SOLUTION

Option 2

Custom new solution created by our subject matter experts

GET A QUOTE

rated 5 stars

Purchased 7 times

Completion Status 100%