question archive Given the following data, calculate the projected available balance and the planned MPS receipts

Given the following data, calculate the projected available balance and the planned MPS receipts

Subject:BusinessPrice:3.87 Bought7

Given the following data, calculate the projected available balance and the planned MPS receipts. The lot size is 100. The demand time fence is 2 weeks.

Week 

Forecast 

50 

50 

50 

50 

Customer Orders 

60 

30 

65 

25 

Proected Available Balance      60 

 

Option 1

Low Cost Option
Download this past answer in few clicks

3.87 USD

PURCHASE SOLUTION

Option 2

Custom new solution created by our subject matter experts

GET A QUOTE

rated 5 stars

Purchased 7 times

Completion Status 100%