question archive Given the following data, calculate the projected available balance and the planned MPS receipts
Subject:BusinessPrice:3.87 Bought7
Given the following data, calculate the projected available balance and the planned MPS receipts. The lot size is 100. The demand time fence is 2 weeks.
Week
1
2
3
4
Forecast
50
50
50
50
Customer Orders
60
30
65
25
Proected Available Balance 60
Answer:
PAB= prior period PAB or on-hand balance + MPS - Customer orders
Therefore:
Week 1 MPS= 60-60 = 0
Week 1 PAB= 60+0-60= 0
Week 2 PAB= 0+100-30= 70
For week 3, use forecast as demand time fence is not applicable
Week 3 PAB= 70+0-50= 20
Week 4 PAB = 20+100-50= 70
Step-by-step explanation
PAB (Projected Available Balance) refers to the running total of readily available inventory minus requirements plus scheduled receipts and planned orders. In this case, since the period is before or after demand time fence, and the lot size is 100, the demand time fence falls under 2 weeks. This time fence is based on customer order and not forecast.
It is important to schedule MPS of 100 units as the available 25 units is not enough to meet the customer order.