question archive Quad Enterprises is considering a new three-year expansion project that requires an initial fixed asset investment of $2
Subject:BusinessPrice:2.87 Bought7
Quad Enterprises is considering a new three-year expansion project that requires an initial fixed asset investment of $2.29 million. The fixed asset will be depreciated straight-line to zero over its three-year tax life. The project is estimated to generate $1,810,000 in annual sales, with costs of $720,000. The project requires an initial investment in net working capital of $450,000, and the fixed asset will have a market value of $480,000 at the end of the project.
a.If the tax rate is 25 percent, what is the project's Year 0 net cash flow? Year 1? Year 2? Year 3? (Do not round intermediate calculations and enter your answers in dollars, not millions of dollars, e.g., 1,234,567. A negative answer should be indicated by a minus sign.)
?b.If the required return is 12 percent, what is the project's NPV? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.)
Answer:
a. Cash Flow
Year 0 = -$2,740,000
Year 1 = $1,008,333.33
Year 2 = $1,008,333.33
Year 3 = $1,818,333.33
b. NPV = $258,388.53
Step-by-step explanation
a.The cash flow of year 0, year 1, year 2, and year 3 is calculated as follows:
Year 0 1 2 3
Annual sales $1,810,000 $1,810,000 $1,810,000
Less: costs $720,000 $720,000 $720,000
Less: depreciation $763,333.33 $766,333.33 $766,333.33
Earnings before tax $326,666.67 $326,666.67 $326,666.67
Less: t..x@25% $81,666.67 $81,666.67 $81,666.67
Earning after tax $245,000 $245,000 $245,000
Add: Depreciation $763,333.33 $766,333.33 $766,333.33
Operating cash flow $1,008,333.33 $1,008,333.33 $1,008,333.33
Initial investment -$2,290,000
Working capital -$450,000 $450,000
After tax salvage value $360,000
Cash flows -$2,740,000 $1,008,333.33 $1,008,333.33 $1,818,333.33
PV F..(@12%) 1 0.89286 0.797198 0.71178
Present value -$2,740,000 $900,297.62 $803,837.16 $1,294,253.75
Where,
After tax salvage value of plant is calculated as follows:
Salvage value of plant $480,000
Book value on date of sale $0
Profit on sale $480,000
Salvage value $480,000
Less: tax on gain $120,000
After tax salvage value $360,000
b. The NPV of the project is calculated as follows:
NPV = Present value of cash inflow - Present value of cash outflow
= $2,998,388.53 - $2,740,000
= $258,388.53