question archive The factors for planning a successful EHR implementation are below including each activity's duration and predecessor(s): Draw the PERT or GANTT chart for this implementation Indicate the critical path on the PERT or GANTT chart Activity Duration (days) Predicessor A Create the EHR vision 5 - B Identify the planning horizon 10 A C Obtain buy-in from affected parties 30 B D Develop a financing and acqusition strategy 10 C E Develop functional, datda, and technical strategies 45 C F Conduct vendor selection 45 D,E G Plan the EHR implementation 15 C,E, F H Conduct benefits realization study 10 A- H
Subject:Computer SciencePrice:2.87 Bought7
The factors for planning a successful EHR implementation are below including each activity's duration and predecessor(s): Draw the PERT or GANTT chart for this implementation Indicate the critical path on the PERT or GANTT chart
|
Activity |
Duration (days) |
Predicessor |
A |
Create the EHR vision |
5 |
- |
B |
Identify the planning horizon |
10 |
A |
C |
Obtain buy-in from affected parties |
30 |
B |
D |
Develop a financing and acqusition strategy |
10 |
C |
E |
Develop functional, datda, and technical strategies |
45 |
C |
F |
Conduct vendor selection |
45 |
D,E |
G |
Plan the EHR implementation |
15 |
C,E, F |
H |
Conduct benefits realization study |
10 |
A- H |