question archive You are managing a project and using the earned value method to manage the budget

You are managing a project and using the earned value method to manage the budget

Subject:Project ManagementPrice:2.86 Bought4

You are managing a project and using the earned value method to manage the budget. You want to prevent the tendency for team members to inflate their "percent complete" estimates. What can you do to try to get the most accurate estimates?

Require all estimates to be approved by the head of the department.

Require an audit from a third-party to ensure accuracy.

None of these methods is appropriate

Keep work packages small in terms of scope and duration.

 

Option 1

Low Cost Option
Download this past answer in few clicks

2.86 USD

PURCHASE SOLUTION

Option 2

Custom new solution created by our subject matter experts

GET A QUOTE

rated 5 stars

Purchased 4 times

Completion Status 100%