Develop the network activity chart and identify the critical path for a project based on the following information. Redraw the activity network as a Gantt chart. What is the expected duration of the project?

Activity          Expected Duration         Predecessors

A                       5 days                                —

B                       6 days                               A

C                      2 days                               A

D                      4 days                               A

E                      6 days                             B, C

F                      6 days                             D, E

G                    12 days                            F

H                     4 days                             G

I                       6 days                             F

J                     7 days                              H, I