question archive The information about six jobs are provides in the following table: Job Description Processing Time (days) Due Date A 6 17 B 3 9 C 4 6 D 11 18 E 9 12 F 7 11 If you were to sequence these jobs according to the shortest process time, what would be the average work-in-process inventory?
Subject:Operations ManagementPrice:2.86 Bought6
The information about six jobs are provides in the following table:
Job Description |
Processing Time (days) |
Due Date |
A |
6 |
17 |
B |
3 |
9 |
C |
4 |
6 |
D |
11 |
18 |
E |
9 |
12 |
F |
7 |
11 |
If you were to sequence these jobs according to the shortest process time, what would be the average work-in-process inventory?
Step 1 :
Step 2 :
Now, As per Shortest Process time Sequencing rule , The the job with the shortest processing time should be done first and subsequently prioritizes the jobs as per their processing times.
Hence,
The Average Work in process Inventory = 2.8
Please see the attached file for the complete solution