question archive 2) According to statistics of a company, the designed production capacity Qd is 1,000,000 pieces, the fixed cost is 5,800,000 yuan per year, unit price is 60 yuan, and the variable cost per unit is 40 yuan
Subject:Civil EngineeringPrice: Bought3
2) According to statistics of a company, the designed production capacity Qd is 1,000,000 pieces, the fixed
cost is 5,800,000 yuan per year, unit price is 60 yuan, and the variable cost per unit is 40 yuan. Questions: (1)
Calculate the BEPQ; (7 points) (2) Calculating the BEPp. (7points)