question archive Time left 2 58:14 Question 13 Norvet wered Medecto 1000 Pro que The city's engineering department is planning to build a recycling facility to help address the issue of waste management
Subject:EconomicsPrice: Bought3
Time left 2 58:14 Question 13 Norvet wered Medecto 1000 Pro que The city's engineering department is planning to build a recycling facility to help address the issue of waste management. The projects ital cost is approximately Php 5,000,000.00. At the end of every 7 years, an additional investment of Php 500,000.00 would be needed. The facility will require Php500,000.00 to operate annually including salary and other costs for the first 6 years. This will eventually increase to 1,000,000.00 as the facility expands. Furthermore, recycling equipment would have to be replaced every 15 years and this costs approimately Php 200,000.00 a) Draw a cash flow diagram. b) What is the capitalized cost of this project? Type the answer for letter b on the textbox. For attachments, place your name and signature beside your answer. 7 ? 1 SS B - % I