During June, Plowers Company accumulated 24,000 hours of direct labor costs on Job 30 and 3,000 hours on Job 32. The total direct labor was incurred at a rate of $22 per direct labor hour for Job 30 and $20 per direct labor hour for Job 32. Journalize the entry to record the flow of labor costs into production during June.

pur-new-sol

Purchase A New Answer

Custom new solution created by our subject matter experts

GET A QUOTE

Answer Preview

Work in Process................................................................................. 112,800*

 

 

Wages Payable.......................................................................... 112,800

 

 

 

 

 

*Job 30 $ 52,800 = 2,400 hours × $22

 

 

Job 32 60,000 = 3,000 hours × $20

 

 

Total $112,800