question archive 1)The probability 3 points that the project will be completed from 13 to 14 weeks is: Q#3: Refer to Q#1, If the optimistic, 4 points most often and pessimistic times of activity b (Erect building) is reduced by 50%

1)The probability 3 points that the project will be completed from 13 to 14 weeks is: Q#3: Refer to Q#1, If the optimistic, 4 points most often and pessimistic times of activity b (Erect building) is reduced by 50%

Subject:BusinessPrice: Bought3

1)The probability 3 points that the project will be completed from 13 to 14 weeks is: Q#3: Refer to Q#1, If the optimistic, 4 points most often and pessimistic times of activity b (Erect building) is reduced by 50%. then probability that the project will be completed in at least 14 weeks is: o 11% 21% 31% 000

2)A farm owner is going to erect a 3 points maintenance building with a connecting electrical generator and water tank. The activities, activity descriptions, and estimated durations are given in the following table. The project network of this scenario is: Activity Activity Description Activity Predecessor Duration (Weeks) m Excavate N Erect building Install generator WHWUH NAG Install tank Install maintenance 4 equipment Connect generator & b, c, d 5 6 tank to building Paint finish W HN Check out facility e, f o OK O Option 1 ! O

pur-new-sol

Purchase A New Answer

Custom new solution created by our subject matter experts

GET A QUOTE

Related Questions