question archive A firm is evaluating two projects

A firm is evaluating two projects

Subject:BusinessPrice:2.87 Bought7

A firm is evaluating two projects. The firm's cost of capital (appropriate discount rate) has been determined to be 9%, and the projects have the following initial investments and cash flows. Initial Investment Cash Flows 1 2 3 4

Project O P50,000 P20,000 P25,000 P15,000 P20,000

Project Y 248,000 P30,000 P35,000 240,000 P10,000

1. Determine the NPV of each project 

2. Which project should the company pursue? Why?

pur-new-sol

Purchase A New Answer

Custom new solution created by our subject matter experts

GET A QUOTE

Answer Preview

Answer:

Npv :- project O = 15,141.5

project Y = 46,953.5

Answer :- Y

Reason :- project Y has HIGH npv i.e 31,812 (46,953.5-15,141.5)

Please see the attached file:

https://drive.google.com/file/d/197aPMmehKdOrvABi3vCeOFebH1_tIQhA/view?usp=sharing