question archive A Company produces tables For producing one table, we must manufacture and cut (internally) the top (1 m3 wood) and the four legs (0,1 m3 wood each) and for the final assembly we will take these five parts as well 5 screws type A, 10 screws type B and 15 nuts type C per table
Subject:BusinessPrice: Bought3
A Company produces tables
For producing one table, we must manufacture and cut (internally) the top (1 m3 wood) and the four legs (0,1 m3 wood each) and for the final assembly we will take these five parts as well 5 screws type A, 10 screws type B and 15 nuts type C per table.
Wood, screws and nuts are bought to an external supplier
1) Describe the BOM
2) Show an MRP for producing 100 tables considering that
a) Delivery time for screws and nuts is one week
b) Lead time for producing boards and legs is two weeks
c) We must deliver the tables in 6 weeks from now on