question archive Given a positive discount rate, which one of the following changes would increase the NPV of a project? Multiple Choice Reducing the amount of working capital that is needed

Given a positive discount rate, which one of the following changes would increase the NPV of a project? Multiple Choice Reducing the amount of working capital that is needed

Subject:FinancePrice:2.86 Bought9

Given a positive discount rate, which one of the following changes would increase the NPV of a project?

Multiple Choice

  • Reducing the amount of working capital that is needed.

  • Spreading the total cash inflows over a longer time interval.

  • Increasing the project's estimated expenses.

  • Increasing the firm's opportunity cost of capital.

pur-new-sol

Purchase A New Answer

Custom new solution created by our subject matter experts

GET A QUOTE

Answer Preview

Reducing the amount of working capital that is needed would increase NPV.
This is because working capital is invested at beginning of project and recovered at end of the project.
Present value factors is high at beginning thus present value of cash outflow is higher
However present value factor is low at end of project thus present value of cash inflows is lower
Thus difference between PVCO and PVCI in relation to working capital would fall if work capital is reduced which would result in increase in NPV since NPV is PVCI - PVCO
 
Spreading the total cash inflows over a longer time interval would decrease NPV as present value of cash inflows would fall
Increasing the project's estimated expenses would decrease NPV since PVCO would increase
Increasing the firm's opportunity cost of capital. Would decrease PVCI
 
PVCO = Present value of cash outflows
PVCI = Present value of cash inflows
NPV = Net present value