question archive Need help on the quiz  GSGM7334 Project Management   37

Need help on the quiz  GSGM7334 Project Management   37

Subject:ManagementPrice:9.82 Bought3

Need help on the quiz 

GSGM7334 Project Management

 

37. When determining which activity to crash, there are other factors that should be assessed beyond cost. Which of the following is NOT one of these factors?

A. The inherent risk associated with the activity

B. How crashing will impact the morale and motivation of the individuals working on that activity

C. Resource availability after crashing that activity

D. The level of difficulty involved in completing the activity

E. When during the project the activity will occur

 

38. Reducing project duration

A. Involves crashing all activities to their crash point

B. Can only be done when resources are not constrained

C. Is always more expensive

D. Tends to increase network sensitivity
E. Should be considered for all projects

 

39. Sometimes very high __________ costs are recognized before a project begins and reducing these costs through shorter project durations becomes a high priority.

A. Labor
B. Direct

C. Project

D. Overhead

E. Interest

 

40. Which of the following projects would be least benefited if additional resources were added?

A. Splitting and stacking a cord of wood

B. Developing new software

C. Harvesting a crop by hand

D. Building a cabin

E. Moving to a new house

 

41. All of the following are disadvantages of scheduling overtime EXCEPT

A. Overtime is associated with additional costs of coordination and communication

B. Sustained overtime work by salaried employees may incur burnout

C. Productivity is reduced the longer one is working

D. More hours results in higher expenses if paying workers hourly

E. Continued overtime can lead to a higher turnover rate

42. Which of the following is NOT a technique for accelerating project completion when resources are not constrained?

A. Assign additional staff and equipment

B. Establish a core team

C. Do it twice-first fast and then correctly

D. Reduce project scope

E. Compromise quality

 

43. In monitoring project time (schedule) performance, actual performance should be compared to

A. Budgets for the current year

B. Top management's targets

C. Project network schedule derived from the WBS/OBS

D. Progress on similar past projects

E. Previous status reports

 

44. The earned value system starts with the time-phased costs that provide the project baseline, which is called the

A. Planned budgeted value of work scheduled

B. Planned budgeted value of work completed

C. Earned value of work scheduled

D. Scheduled value of work scheduled

E. Scheduled value of work completed

 

45. The earned value of a project is the

A. Project cost to date adjusted for project scope changes

B. Total project cost to date

C. Cost incurred minus the planned cost

D. Percent of the original budget that has been earned by actual work

E. The planned time-phased baseline of the value of work scheduled

 

46. The cost variance for a project is calculated by

A. EV - AC

B. AC - SV

C. PV - EV

D. CV - EV

E. EV - PV

 

47. The schedule variance for a project is calculated by:

A. EV - AC

B. AC - SV

C. PV - EV

D. CV - EV

E. EV - PV

 

48. Baseline project budgets are derived from

A. The organization's overall budget

B. Time-phasing the work packages

C. Top management directions

D. The total direct, direct project overhead and G&A overhead costs

E. The earned value system

pur-new-sol

Purchase A New Answer

Custom new solution created by our subject matter experts

GET A QUOTE

Answer Preview

Q 37

D. The level of difficulty involved in completing the activity 

 

 When determining which activity to crash, there are other factors that should be assessed beyond cost. These factors include the inherent risk associated with the activity, how crashing will impact the morale and motivation of the individuals working on that activity, resource availability after crashing that activity, and the level of difficulty involved in completing the activity.

 

Q38

A. Involves crashing all activities to their crash point

 

Reducing project duration can involve crashing all activities to their crash point. This can only be done when resources are not constrained. Reducing project duration is always more expensive. Reducing project duration tends to increase network sensitivity. Reducing project duration should be considered for all projects.

 

Q39

D. Overhead 

Overhead costs, also known as overhead or operating expenses, are expenses associated with running a business that are not directly related to the creation or production of a product or service. They are the expenses incurred by the business in order to remain in business, regardless of its level of success.

 

Q40

C. Harvesting a crop by hand

 

 If additional resources were added to the project of harvesting a crop by hand, it would be less benefited because it would be more difficult to harvest the crop with more people helping.

 

Q41

E. Continued overtime can lead to a higher turnover rate 


Q42

D. Reduce project scope 

 

 Reducing project scope is not a technique for accelerating project completion when resources are not constrained. Some possible techniques include assigning additional staff and equipment, establishing a core team, doing it twice-first fast and then correctly, and compromising quality.

 

Q43

C. Project network schedule derived from the WBS/OBS 

 

 The project network schedule derived from the WBS/OBS is the most accurate comparison of actual performance to schedule.

 

Q44

C. Earned value of work scheduled  

 

The earned value system starts with the time-phased costs that provide the project baseline, which is called the earned value.

 

Q45

D. Percent of the original budget that has been earned by actual work

 

The earned value of a project is the percentage of the original budget that has been earned by actual work completed. It is calculated by dividing the earned value by the budget at completion.

 

Q46

A. EV - AC

 

Q47

E. EV - PV

 

Q4 

B. Time-phasing the work packages