Suad Alwan, the purchasing agent for Dubai Airlines, has determined that the second plane took 16,000 hours to produce

Subject:BusinessPrice:9.82 Bought3

Suad Alwan, the purchasing agent for Dubai Airlines, has determined that the second plane took 16,000 hours to produce. Using an 80% learning curve and a $35-per—hour labor charge, he wants to determine the cost of the six additional planes. Time required for the sixth unit = 11,240 hours (round your response to the nearest whole number). Cost of the sixth unit 2 393,400 dollars (round your response to the nearest whole number). Time required for the seventh unit = 10,690 hours (round your response to the nearest whole number) Cost of the seventh unit 2 dollars (round your response to the nearest whole number).

pur-new-sol

Purchase A New Answer

Custom new solution created by our subject matter experts

GET A QUOTE

Answer Preview

Total Cost of the 7th unit of airplane:

= $374,150( Total Cost of the 7th unit of airplane.)

Step-by-step explanation

The given Data are the following:

 

Labor Charge per hour= $35/hour 

The total labored hours to manufacture the 7th unit= 10,690 hours 

 

To know the total cost of the 7th airplane unit we will need to use this formula:

= Total labored hours to manufacture the 7th unit × labor charge per hour 

 

= 10,690hours × 35 labor charge per hour 

= $ 374,150( The total cost of the 7th airplane unit.)