question archive Suad Alwan, lhe purchasing agent for Dubai Ainines, has determined that the second plane took 16,000 hours to produce

Suad Alwan, lhe purchasing agent for Dubai Ainines, has determined that the second plane took 16,000 hours to produce

Subject:BusinessPrice:9.82 Bought3

Suad Alwan, lhe purchasing agent for Dubai Ainines, has determined that the second plane took 16,000 hours to produce. Using an 80% learning curve and a $35-per—hour labor charge, he wants to determine the cost of the six additional planes. 11me required [or the sixth unlt = 11,240 hours (round your response to the nearest whole number). Cost of the sixth unii : 393,400 dollars (round your response to the nearest whole number). Time required [or the seventh unit = 10,690 hours (round your response to the nearest whole number)' Cost of the seventh unit = dollars (round your response to the nearest whole number).

Option 1

Low Cost Option
Download this past answer in few clicks

9.82 USD

PURCHASE SOLUTION

Option 2

Custom new solution created by our subject matter experts

GET A QUOTE

rated 5 stars

Purchased 3 times

Completion Status 100%

Related Questions