question archive Suad Alwan, lhe purchasing agent for Dubai Ainines, has determined that the second plane took 16,000 hours to produce
Subject:BusinessPrice:9.82 Bought3
Suad Alwan, lhe purchasing agent for Dubai Ainines, has determined that the second plane took 16,000 hours to produce. Using an 80% learning curve and a $35-per—hour labor charge, he wants to determine the cost of the six additional planes. 11me required [or the sixth unlt = 11,240 hours (round your response to the nearest whole number). Cost of the sixth unii : 393,400 dollars (round your response to the nearest whole number). Time required [or the seventh unit = 10,690 hours (round your response to the nearest whole number)' Cost of the seventh unit = dollars (round your response to the nearest whole number).
Purchased 3 times