question archive Oaklis Company has provided the following data for maintenance cost: Maintenance cost is a mixed cost with variable and fixed components
Subject:AccountingPrice: Bought3
Oaklis Company has provided the following data for maintenance cost: Maintenance cost is a mixed cost with variable and fixed components. The fixed and variable components of maintenance cost are closest to what amounts?
Prior Year Current Year Machine Hours 10,000 12,000 Maintenance cost $24,000 $27,600
A. $24,000 per year; $1.80 per machine hour
B. $24,000 per year; $2.30 per machine hour
C. $6,000 per year; $1.80 per machine hour
D. $6,000 per year; $2.30 per machine hour