1) When analysing quality for a project a Project Manager decides to use a tool. This tool provides a creative way to look at the causes or potential causes of a problem. Which tool is the Project Manager planning to use?

2) A Project Manager is using AOA to perform critical path analysis. The network diagram is represented as shown using below. What will represent the path:

Activity Duration Dependent on

A 3 None

C 3 None

B 2 A

D 5 C

E 2 None

F 4 E

G 3 D, F

H 1 D, F

I 2 B, G

R 0 H, I

3) According to Maslow's hierarchy of needs, what is the lowest level which must be met before other levels can be met?

4) You are part of an expert committee deciding which project should be implemented by your company. Your committee asks tough questions from the project teams and helps decide which project your company should select. Which project selection technique are you using.

5) You have just been made the Project Manager of the ABC project. You are trying to read the WBS and are unable to understand some of the WBS components. What should be your first step to understand this?

pur-new-sol

Purchase A New Answer

Custom new solution created by our subject matter experts

GET A QUOTE

Answer Preview

Answer:

  1. Ishikawa diagram
  2. CDGIR  
  3. Physiological level 
  4. Murder Board 
  5. Referring to the WBS dictionary 

Explanation:

  1. The manager is planning to use the Ishikawa diagram
  2. CDGIR is the critical path with the longest pathway of 13 duration 
  3. Physiological level which appears in the lowest in the hierarchy
  4. Murder Board why by the committee gets to ask questions to the project representatives 
  5. Referring to the WBS dictionary since it identifies all components of webs