question archive the life of the project Assume that an alternative has a 3-year life and that you calculated its annual worth over its 3-year lifecycle If you were told to provide the annual worth of that alternative for a 4-year study period, would the annual worth value you calculated from the alternative’s 3-year life cycle be a valid estimate of the annual worth over the 4-year study period? Why or why not?

the life of the project Assume that an alternative has a 3-year life and that you calculated its annual worth over its 3-year lifecycle If you were told to provide the annual worth of that alternative for a 4-year study period, would the annual worth value you calculated from the alternative’s 3-year life cycle be a valid estimate of the annual worth over the 4-year study period? Why or why not?

Subject:Computer SciencePrice: Bought3

the life of the project

Assume that an alternative has a 3-year life and that you
calculated its annual worth over its 3-year lifecycle If you were told to
provide the annual worth of that alternative for a 4-year study period, would
the annual worth value you calculated from the alternative’s 3-year life cycle
be a valid estimate of the annual worth over the 4-year study period? Why or
why not?