CM 4210 ( Construction Contracting ) The contractor chosen by the owner to enter into the contract was the low bidder

Subject:ManagementPrice:2.84 Bought6

CM 4210 ( Construction Contracting )

The contractor chosen by the owner to enter into the contract was the low bidder. In reviewing its bid after the bid opening, the contractor realizes it has made six (6) mistakes. If the contractor corrects the first four mistakes, it will still be the low bidder. However, if it corrects a fifth or sixth mistake it will no longer be the low bidder. Is it ethical for the contractor to only correct four mistakes and still get the contract, or would ethics require correction of all six mistakes?

pur-new-sol

Purchase A New Answer

Custom new solution created by our subject matter experts

GET A QUOTE

Answer Preview

It is unethical for the constructor to correct only four out of the six mistakes. Ethics would request the contractor to make the six corrections and continue with the application even if the bid is not the lowest.

Step-by-step explanation

Ethics is the set of principles that drive people's behavior towards differentiating from actions that are socially considered right or wrong. Fairness, responsibility, respect, caring, or trustworthiness are considered ethical values. In the case provided, it is unethical for the constructor to correct only four out of the six mistakes on the proposal. The contractor would do so to continue being the lower bidder which increases the chances of being selected for the project. However, if he does not make the corrections and eventually wins the contract, during the execution of the program it is highly possible that the hidden mistakes will come to the surface, affecting the project clients and sponsors. Ethics would demand the contractor to make the six corrections and continue with the application even if the bid is not the lowest after the modifications. One of the obligations of contractors is to disclose precise information about the expenditures they will incur. In front of the failure of the contractor, the client could request the contract to be voided because of his unilateral mistake.