Problem 3) The following project is at the end of its 6th week

Subject:StatisticsPrice:8.89 Bought3

Problem 3) The following project is at the end of its 6th week. Find the cost and schedule variances. Also find the CPI and SPI. Then find the critical ratio of the project using earned value calculations. Finally, calculate the EAC for the project by at least two different methods.

 

 

Activity

Predecessor

Duration(wks)

Budget($)

Actual cost($)

%complete

A

-

2

600

400

100

B

-

3

150

180

100

C

A

2

250

300

100

D

A

5

500

400

20

e

B, c

4

400

200

20

 

 

 

a.     CV = 

b.     SV = 

c.      CPI = 

d.     SPI= 

e.     CR= 

f.      EAC= 

Option 1

Low Cost Option
Download this past answer in few clicks

8.89 USD

PURCHASE SOLUTION

Option 2

Custom new solution created by our subject matter experts

GET A QUOTE

rated 5 stars

Purchased 3 times

Completion Status 100%

Related Questions