Problem 3) The following project is at the end of its 6th week. Find the cost and schedule variances. Also find the CPI and SPI. Then find the critical ratio of the project using earned value calculations. Finally, calculate the EAC for the project by at least two different methods.

 

 

Activity

Predecessor

Duration(wks)

Budget($)

Actual cost($)

%complete

A

-

2

600

400

100

B

-

3

150

180

100

C

A

2

250

300

100

D

A

5

500

400

20

e

B, c

4

400

200

20

 

 

 

a.     CV = 

b.     SV = 

c.      CPI = 

d.     SPI= 

e.     CR= 

f.      EAC= 

pur-new-sol

Purchase A New Answer

Custom new solution created by our subject matter experts

GET A QUOTE

Answer Preview

a.     CV =  -300

 

b.     SV =  -420

 

c.      CPI = 0.7973

 

d.     SPI= 0.7375

 

e.     CR= 0.5880

 

f.      EAC = 2383

= 2200

 

From the table given in the question we can find: planned value , earned value and actual cost which will help us in the calculations below.

 

Planned value (PV) = actual budget = 1600

Earned value (EV) = Actual percentage x project budget

= (100% x 600)+(100% x 150)+(100% x 250)+(20% x 500)+(20% x 400) = 1180

Actual cost (AC) = 1480

 

a) CV = earned value - actual

= 1180 - 1480

 

=-300

 

b) SV = earned value - planned value

= 1180 - 1600

 

= -420

 

c) CPI = Earned value / Actual value

= 1180/1480

 

= 0.7973

 

d) SPI = Earned value /Planned value

= 1180/1600

 

=0.7375

 

e) CR = CPI*SPI

= 0.7973 x 0.7375

 

= 0.5880

 

f) EAC can be found by the use of either of the following formulas

EAC = total budget / CPI

= 1900/0.7973

 

= 2383

 

EAC = Actual budget +(total budget - earned value)

= 1480+ (1900- 1180)

 

= 2200