question archive Problem 3) The following project is at the end of its 6th week
Subject:StatisticsPrice:8.89 Bought3
Problem 3) The following project is at the end of its 6th week. Find the cost and schedule variances. Also find the CPI and SPI. Then find the critical ratio of the project using earned value calculations. Finally, calculate the EAC for the project by at least two different methods.
Activity |
Predecessor |
Duration(wks) |
Budget($) |
Actual cost($) |
%complete |
A |
- |
2 |
600 |
400 |
100 |
B |
- |
3 |
150 |
180 |
100 |
C |
A |
2 |
250 |
300 |
100 |
D |
A |
5 |
500 |
400 |
20 |
e |
B, c |
4 |
400 |
200 |
20 |
a. CV =
b. SV =
c. CPI =
d. SPI=
e. CR=
f. EAC=