question archive Using the following initial cost and cash flow figures below for Projects 1 and 2, please answer the three questions (a, b, and c)

Using the following initial cost and cash flow figures below for Projects 1 and 2, please answer the three questions (a, b, and c)

Subject:FinancePrice:2.84 Bought7

Using the following initial cost and cash flow figures below for Projects 1 and 2, please answer the three questions (a, b, and c).

 

                                 Expected Net Cash Flows

 Year                   Project 1                                Project 2

  0                    -$1,000,000                         -$1,000,000

  1                        520,000                                 150,000

  2                        300,000                                 425,000

  3                        280,000                                 800,000

 

Both of the projects have a cost of capital (r) of 11.5 percent (so r = 0.115 in decimal form).

 

a) What is Project 1's net present value (NPV)? Based on your answer for the NPV, should this project be accepted or rejected? Briefly explain.

 

b) Rounding your answer to the second decimal place, what is Project 2's internal rate of return (IRR)? Based on your answer for the IRR, should this project be accepted or rejected? Briefly explain.

 

c) Finally, what is the payback period (in years) for Project 2?

pur-new-sol

Purchase A New Answer

Custom new solution created by our subject matter experts

GET A QUOTE

Answer Preview

a) What is Project 1's net present value (NPV)? Based on your answer for the NPV, should this project be accepted or rejected? Briefly explain.

 

NPV of Project-1 =  $ (90,332.74)

NPV of Project-2 = $ 53,501.01 

 

Hence

As per above calculation we should accept the Project-2, since NPV of this project is positive.

 

 

b) Rounding your answer to the second decimal place, what is Project 2's internal rate of return (IRR)? Based on your answer for the IRR, should this project be accepted or rejected? Briefly explain.

 

Therefore

IRR = 0.1397 OR 13.97%

 

Since the IRR(i.e.13.97%) is greater than Cost of capital (i.e.11.5%) we should accept the Project-2

 

c) Finally, what is the payback period (in years) for Project 2?

 

 

Payback Period = 2.53 Years

 

 

For further doubt if any feel free to ask in comment section, if you find my answer helpful please rate it as helpful which will motivate me to do better work.

Thank You..

 

 

Step-by-step explanation

a) What is Project 1's net present value (NPV)? Based on your answer for the NPV, should this project be accepted or rejected? Briefly explain.

 

Cost of capital = 11.5%

 

Calculation of Net Present Value of Projects

Year Cash Flows PVF(11.5%,Year) Present Values
Project -1  Project-2 Project -1  Project-2
0  $ (1,000,000.00)  $ (1,000,000.00) 1.000  $     (1,000,000.00)  $     (1,000,000.00)
1  $        520,000.00   $        150,000.00  0.897  $           466,367.71   $           134,529.15 
2  $        300,000.00   $        425,000.00  0.804  $           241,307.89   $           341,852.84 
3  $        280,000.00   $        800,000.00  0.721  $           201,991.66   $           577,119.02 
Net Present Value  $           (90,332.74)  $             53,501.01 

 

Therefore

NPV of Project-1 =  $ (90,332.74)

NPV of Project-2 = $ 53,501.01 

 

Hence

As per above calculation we should accept the Project-2, since NPV of this project is positive.

 

 

b) Rounding your answer to the second decimal place, what is Project 2's internal rate of return (IRR)? Based on your answer for the IRR, should this project be accepted or rejected? Briefly explain.

 

 

As per formula

 

IRR = Lower Rate + [NPV at Lower Rate/(NPV at Lower Rate-NPV at Higher Rate)]*(Higher Rate - Lower Rate)

 

Where

Lower Rate = 12% (Assumed)

Higher Rate = 15% (Assumed)

 

Note- We can assume any rate as lower rate and higher rate but i suggest you always try to select two rates which have difference not more than 3-5% and higher rate give us negative NPV and Lower rate give us positive NPV.

 

 

NPV of Project-2 at above rates

Year Project -1  PVF(15%,Year) Present Value PVF(12%,Year) Present Value
0  $ (1,000,000.00) 1.000  $       (1,000,000.00) 1.000  $     (1,000,000.00)
1  $        150,000.00  0.870  $             130,434.78  0.893  $           133,928.57 
2  $        425,000.00  0.756  $             321,361.06  0.797  $           338,807.40 
3  $        800,000.00  0.658  $             526,012.99  0.712  $           569,424.20 
Net Present Value  $             (22,191.17)    $             42,160.17 

 

Therefore

 

IRR = Lower Rate + [NPV at Lower Rate/(NPV at Lower Rate-NPV at Higher Rate)]*(Higher Rate - Lower Rate)

         = 0.12 + [42,160.17/(42,160.17+22,191.17)]*(0.15 - 0.12)

         = 0.12 + (0.6515*0.03)

         = 0.12 + 0.0197

         = 0.1397

 

Therefore

IRR = 0.1397 OR 13.97%

 

Since the IRR(i.e.13.97%) is greater than Cost of capital (i.e.11.5%) we should accept the Project-2

 

 

c) Finally, what is the payback period (in years) for Project 2?

  

Calculation of Payback period     

Year Project -2 Accumulated Cash Flow
0  $ (1,000,000.00)  $                  (1,000,000.00)
1  $        150,000.00   $                      (850,000.00)
2  $        425,000.00   $                      (425,000.00)
3  $        800,000.00   $                        375,000.00 

 

 

Payback Period = (T-1) + 1(CFr - CF)

Where

T = Year in which Accumulated Cash Flow is positive i.e. 3

CFr = ash Flow required in 3rd Year where Accumulated Balance become 0 i.e. $425,000.00

CF = Total Cash flow in 3rd year i.e. $800,000

 

Therefore

 

Payback Period = (T-1) + 1(CFr - CF)

                            = (3-1) + 1(425,000 - 800,000.00)

                            = 2 + 0.53

                            = 2.53 Years

 

Payback Period = 2.53 Years