question archive Scenario 3: Parts-R-Us A supplier to Toyota stamps out parts using a press
Subject:ManagementPrice:2.84 Bought7
Scenario 3: Parts-R-Us
A supplier to Toyota stamps out parts using a press. Changing a part type requires the supplier to change a die on the press. This changeover currently takes two hours. The supplier estimates that each hour spent on the changeover costs $250. Demand for parts is 1,000 per month. Each part costs the supplier $100, and the supplier incurs an annual holding cost of 20%.
1)Determine the optimal production batch size for the supplier.
2)Toyota wants the supplier to reduce its batch size by a factor of 4; that is, if the supplier currently produces Q parts per batch, Toyota would like them to produce Q/4 parts per batch. What should the supplier do in order to achieve this result? In other words, what setup time creates a scenario in which the optimal batch size drops to 1⁄4 of its current level?
1.)
Given:
Annual demand = 12*1000 = 12000
Fixed setup cost, S = 2*250 = $500
Holding cost, H = 100*20% = $20
Formula:
Optimal production batch size, Q = SQRT(2DS/H)
Solution:
Q = SQRT(2*12000*500/20)
Q = 774.59 (rounded off to whole number)
Answer:
Q = 775
2.)
Target batch size as per Toyota requirement = Q/4 = 775/4 = 193.75
In the equation of EOQ, we see that Batch size (Q) is directly proportional to square root of setup cost.
Therefore, if Q is reduced by a factor of 4, then setup cost should reduce by a factor of 16 as shown below:
Target setup cost = 500/16 = $31.25
Given that each hour the setup costs = $250
Solution:
Therefore, target setup time = 31.25 / 250
Target setup time = 0.125 hours (convert to minutes, multiply by 60)
Target setup time = 7.5 minutes
Answer:
Therefore, supplier should achieve a setup time of 7.5 minutes so that optimal batch size drops to 1/4th of its current level.
Step-by-step explanation
Already explained above. Hope it helps you a lot. Thank you.