A local project being analyzed by PERT has 42? activities, 13 of which
are on the critical path. If the estimated time along the critical path is 105 days with a project variance of? 25, what is the probability that the project will be completed in 95 days or? more?
A.
−0.40000
B.
0.02275
C.
0.97725
D.
0.34444
E.
4.20000