Q: A local project being analyzed by PERT has 42? activities, 13 of which are on the critical path

Subject:ManagementPrice: Bought3

Q: A local project being analyzed by PERT has 42? activities, 13 of which are on the critical path. If the estimated time along the critical path is 105 days with a project variance of? 25, what is the probability that the project will be completed in 95 days or? more?

 

A.

−0.40000

 

B.

0.02275

 

C.

0.97725

 

D.

0.34444

 

E.

4.20000

 

 

 

IF they asked what is the probability that the project will be completed in 95 days or? less, this is how you would solve it.. but how about if they ask if its morejQuery22406618313643543086_1595797288542