question archive The project information for the customer order project of the Computer Company is presented as follow

The project information for the customer order project of the Computer Company is presented as follow

Subject:Project ManagementPrice:3.86 Bought8

  1. The project information for the customer order project of the Computer Company is presented as follow.

ID

Activity

Predecessor 

Time 

A

Order review

None 

3

B

Order standard parts

A

4

C

Produce standard parts 

A

2

D

Design custom parts 

B

5

E

Software development 

C

4

F

Manufacturing hardware

C

3

G

Assemble 

D, E

3

H

Test

F, G

5

J

Packaging 

H

4

 

  Use the above table 

  1. Complete the task network.
  2. Find Earliest Activity Times (Earliest Start and Earliest Finish) using Forward Pass.
  3. Find Latest Activity Times (Latest Start and Latest Finish) using Backward Pass.
  4. Identify and calculate the length of the critical path.
  5. Calculate the Free Slack (FS) of each activity 
  6. Calculate the Total Slack (TS) of each activity

 

Option 1

Low Cost Option
Download this past answer in few clicks

3.86 USD

PURCHASE SOLUTION

Option 2

Custom new solution created by our subject matter experts

GET A QUOTE

rated 5 stars

Purchased 8 times

Completion Status 100%