question archive The project information for the customer order project of the Computer Company is presented as follow
Subject:Project ManagementPrice:3.86 Bought8
ID
Activity
Predecessor
Time
A
Order review
None
3
B
Order standard parts
A
4
C
Produce standard parts
A
2
D
Design custom parts
B
5
E
Software development
C
4
F
Manufacturing hardware
C
3
G
Assemble
D, E
3
H
Test
F, G
5
J
Packaging
H
4
Use the above table
According to the information in the exercise:
The forward and backward pass including the Early Start (ES), Late Start (LS), Early Finish (EF), Late Finish (LF), Total Slack (TS), and Free Slack (FS) is:
The Expected Time (Te) of the project is 24 time units. The critical path of the project contains all the activities with Total Slack (TS) equal to zero (0). Then, the critical path of the project is A-B-D-G-H-J.
Please see the attached file for the complete solution