question archive It's the end of month 4 of your 6 month project and your performance cost reports have arrived

It's the end of month 4 of your 6 month project and your performance cost reports have arrived

Subject:ManagementPrice:3.87 Bought7

It's the end of month 4 of your 6 month project and your performance cost reports have arrived.  So far, your plan is to have $500,000 worth of work to be completed.  Your project team actually accomplished $600,000 worth of work. Total expenditures for the completed work is $650,000.

What is the earned value, actual cost, and planned value?

Option 1

Low Cost Option
Download this past answer in few clicks

3.87 USD

PURCHASE SOLUTION

Option 2

Custom new solution created by our subject matter experts

GET A QUOTE

rated 5 stars

Purchased 7 times

Completion Status 100%

Related Questions