(b) The desired daily output for an assembly line is 360 units. This assembly line will operate 450 minutes per day. The following tasks contain information on this product’s task times and precedence relationships. TASK TASK TIME (SECONDS) IMMEDIATE PREDECESSOR A 30 None B 35 A C 30 A D 35 B E 15 C F 65 C G 40 E,F H 25 D,G Draw the precedence diagram and answer the following questions: