All of the following are inputs to the Plan Procurement process except:
Risk register.
Stakeholder register.
Application area extensions.
Enterprise environmental factors.
15)
The first step in Block's framework of the political process as applied to stakeholder management is to:
Assess your own capabilities
Assess the environment
Identify the goals of the principal actors
Define the problem
16)
External stakeholders that are external to a project but possess the power to effectively disrupt the project's development are:
Intervenor groups
Environmental groups
Stressor groups
Special-interest groups