A local company makes athletic clothing and they are preparing aggregate production plans on a quarterly basis for the coming year for their line of women's wear

Subject:BusinessPrice:2.88 Bought3

A local company makes athletic clothing and they are preparing aggregate production plans on a quarterly basis for the coming year for their line of women's wear. They have the following information available to develop a level capacity and a matching (chase) demand plan: (Assume that pattern of demand repeats each year, that is the demand in quarter 4 of the previous year was 13,000 units) Number of working days per quarter = 65 days Number of hours per day per person = 8 hours Labor to produce one unit = 5 hours Demand for four quarters respectively: 12,300, 12,500, 12,200, 13,000 units

What is the total cost to hire workers under a matching (chase) strategy?

a. $4,500

b. $4,800

c. $6,400

d. $7,200

e. $14,400

pur-new-sol

Purchase A New Answer

Custom new solution created by our subject matter experts

GET A QUOTE

Answer Preview

What is the total cost to hire workers under a matching (chase) strategy?

The correct option is d. $7,200.

Reason:

 

Quarter Demand Unit/Person Required Worker Hired Worker
1 12300 104 119 0
2 12500 104 121 2
3 12200 104 118 0
4 1300 104 125 7
        9

 

The total worker needs to be hired is 9. Therefore, the cost of hiring the worker is:

 

Note: The cost of hiring is assumed to be $800.